Q. With reference to Mumbai-Ahmedabad High-Speed Rail (MAHSR), consider the following statements:
1. It is the India’s first and only approved bullet train.
2. Indian Railways is the implementing agency of the project.
Which of the statements given above is/are correct?
Answer: A
Notes:
- Statement 1 is correct.
- Statement 2 is incorrect: National High Speed Rail Corporation is the implementing agency.
Source: Article