Q. Consider the following statements about the Green Energy Corridor Project for Intra-State Transmission System (InSTS):
1. It aims at synchronizing electricity produced from renewable sources.
2. The GEC-Intra State Transmission System (InSTS) project is sanctioned in 2020-21.
Which of the statements given above is/are not correct?

[A] 1 only

[B] 2 only

[C] Both 1 and 2

[D] Neither 1 nor 2

Answer: B
Notes:

About the Green Energy Corridor Project for Intra-State Transmission System (InSTS):

  • The Green Energy Corridor (GEC) Project aims at synchronizing electricity produced from renewable sources such as solar and wind with conventional power stations in the grid.
  • The GEC-Intra State Transmission System (InSTS) project was sanctioned in 2015-16, for evacuation and integration of the renewable energy capacity through setting up of transmission lines and increasing transformation capacity of substations.

Source: EPIC January 2022