Q. Who are responsible for the public consultation process of EIA?
Explanation: The public hearing is a mandatory step in the process of environmental clearance for certain developmental projects. This provides a legal space for people of an area to come face-to-face with the project proponent and the government and express their concerns.
The process of public hearing is conducted prior to the issue of NOC from SPCB. The District Collector is the chairperson of the public hearing committee. Other members of the committee includes the official from the district development body, SPCB, Department of Environment and Forest, Taluka and Gram Panchayat representative, and senior citizen of the district, etc. The hearing committee hears the objections/suggestions from the public and after inserting certain clauses it is passed on to the next stage of approval (Ministry of Forest and Environment).