ForumIAS LATEST
- 04 June | MGP Strategy Series | GS Paper 4 (Ethics) with AIR 7 A.R. Rajah Mohaideen Click Here to register for the session →
- 04 June | GS Advance Program begins from 4th June 2026 | First 2 classes open to all Click Here to register for the event →
- 05 June | MGP Strategy Series | GS Paper 3 Strategy Session with AIR 406 Mannat Luthra Click Here to register for the session
- 06 June | Open Orientation on Essay Guidance Program (EGP 2026) Click Here to register →
- 07 June | Open Orientation for Current Affairs for Mains 2026 Click Here to register →
- 07 June | Sociology Optional Strategy Session with AIR 10 Ujjwal Priyank Click Here to register →
India’s first river interlinking project caught in U.P.-M.P. tussle
News:
- Number of issues has been hindering the Ken-Betwa Project- the first river-interlinking project in India
Important facts:
- The project will transfer surplus water from Ken River to Betwa Basin

- Two phases:
- 1st phase involves the building of Dhaudhan dam, and a 230km long canal for transferring water from the Ken River to Bundelkhand region of Uttar Pradesh and Madhya Pradesh.
- 2nd Phase: local water management projects- the Kotha barrage, Lower Orr and Bina complex
- Benefits:
- Irrigate drought-prone areas of Bundelkhand Region and adjoining areas
- Meeting drinking water needs
- Major Issues:
- The dispute over water sharing
- The dispute over water sharing between Uttar Pradesh and Madhya Pradesh during the Rabi season
- Madhya Pradesh declined the assumptions of 2005 agreement between U.P and M.P on water sharing
- Madhya Pradesh has demanded inclusion of local water management projects to meet the water needs. These projects are included in the 2nd phase and inclusion in the 1st phase would require fresh environmental appraisals.
- Acquiring non-forest land; environmental concerns
- The project involves deforesting a large portion of the Panna Tiger reserve